August 30th 2003


I kept hitting my head on the luggage racks, so we spent part of the day removing the left side rack so that work could continue on removing the raised floor underneath.  

Removing the raised floor has proven to be much more of a pain than I had thought that it would be.  There has to be an easier way or a tool made for the job.  We're getting frustrated and the floor is only coming out in 4 foot sections...